The BTES 1.0 templates are divided into different types of regime temperature combinations for heating and cooling end-units. To clarify this aspect the different templates are the following.

  • LT heating + HT cooling

  • HT cooling + HT and LT heating separate

  • HT cooling + HT and LT heating together

  • LT heating + LT and HT cooling separate

  • LT heating + LT and HT cooling together

  • HT and LT heating separate + LT and HT cooling separate

  • HT and LT heating together + LT and HT cooling separate

  • HT and LT heating separate + LT and HT cooling together

  • HT and LT heating together + LT and HT cooling together

LT heating + HT cooling

...

Working principle

The working principle of a geothermal system is divided into two main operating conditions, winter and summer. Of course, if there is both heating and cooling demand at the same time, both conditions are active.

...